Road construction and maintenance projects

Allen County

Berm stone placement

State Route 117 between Bowman Road and state Route 309, Lima, will be reduced to one lane in each direction through the work zone for the placement of berm stone. Work will be performed by the ODOT Allen County maintenance garage.

State Route 65 from the Auglaize County line to the Putnam County line will be reduced to one lane through the work zone for the placement of berm stone. Work will be performed by the ODOT Allen County maintenance garage.

Bridge work

Interstate 75, and also Bentley Road and Napoleon Road will be affected during bridge deck replacements on Napoleon Road over Interstate 75, Beaverdam, and Bentley Road over Interstate 75, Bluffton. The following are upcoming impacts related to the project:

Napoleon Road

Napoleon Road bridge over I-75 closed May 22 for approximately four months.

Traffic detoured onto Sugar Creek Road, Swaney Road and Lincoln Highway (state Route 696) back to Napoleon Road.

The northbound exit ramp from Interstate 75 to Napoleon Road closed May 30 for four months.

Traffic detoured north on Interstate 75, east on Lincoln Highway (state Route 696), south on Swaney Road and west on Sugar Creek Road back to Napoleon Road; or west onto Lincoln Highway (state Route 696) back to S. West Street in Beaverdam.

The entrance ramp to Interstate 75 southbound from Napoleon Road will remain open.

Motorists traveling northbound on Interstate 75 wishing to access state Route 696 are advised to do so via exit 135 (state Route 696/U.S. 30) at Beaverdam. No access to state Route 696 from Interstate 75 northbound at the Napoleon Road exit will be available.

Bentley Road (exit 140)

Two bridges on Bentley Road at exit 140 (one over Interstate 75 and one over the railroad north of Interstate 75) closed June 5 for approximately four months.

Both the southbound entrance and exit ramps at Bentley Road also closed on June 5 for four months.

Interstate 75 northbound traffic will be detoured to the state Route 103 (exit 142) interchange back to Bentley Road.

Interstate 75 southbound traffic is advised to access Bentley Road via the state Route 103 interchange (exit 142) and follow state Route 103 through Bluffton back to Bentley Road.

The northbound ramps at the interchange remain open; however, left turns onto Bentley Road from northbound Interstate 75 are not permitted. (See detour map)

Interstate 75

Overnight Thursday, June 15, and Friday, June 16, the main travel lanes of I-75 under Bentley Road, Bluffton, will experience closures from 10 p.m. until 6 a.m. For more information, see the traffic advisory.

Interstate 75 both northbound and southbound will be periodically reduced to one lane at times beneath both the Napoleon Road and Bentley Road bridge structures during certain operations related to construction.

Lane closures will occur sporadically and are expected to occur mostly during daytime hours but some nighttime closures may occur.

Hancock County

Resurfacing

Resurfacing of the following routes within the city of Findlay will restrict traffic to one lane through the work zone. Work is being performed by M&B Asphalt, Old Fort.

U.S. 224 from Broad Street to Main Street

State Route 12 from Interstate 75 to Main Street (section between Western Avenue and Glessner Street closed during daytime hours for a project administered by the city of Findlay)

State Route 37 from Lincoln Avenue to Blanchard Avenue

State Route 568 from Main Street to Beech Avenue

Culvert replacement

U.S. 224 just west of state Route 235, west of Findlay, is scheduled to close July 17 for approximately 30 days for a culvert replacement. Traffic will be detoured onto U.S. 224, state Route 235, state Route 12 and state Route 65 back to U.S. 224. Work is being performed by BCC Ohio, New London.

Pavement repairs

State Route 235 from township Road 89 to McComb will be restricted to one lane through the work zone for pavement repairs. Work is being performed by the ODOT Hancock County maintenance garage.

Bridge repairs

U.S. 68 southbound exit ramp to U.S. 68 southbound over Eagle Creek at state Route 15, south of Findlay, closed May 15 for approximately two months for bridge repair. Traffic detoured onto state Route 15 eastbound to the state Route 37 interchange to state Route 15 westbound back to U.S. 68. Work is being performed by Global Outdoor Solutions, Cleveland. (See detour map)

State Route 12/state Route 235 overlap between state Route 235 and township Road 57, west of Benton Ridge over Moffitt Ditch, closed April 17 for approximately 60 days for repair of a bridge deck. Traffic on state Route 12 detoured onto state Route 235, Interstate 75 northbound back to state Route 12. State Route 235 traffic detoured onto Interstate 75 northbound to state Route 12 back to state Route 235. Work is being performed by Global Outdoor Solutions, Cleveland. (See detour map)

Interstate 75

Findlay

Interstate 75 both northbound and southbound from just south of County Road 313 (approximately mile marker 155) to county Road 99 (mile marker 161) is restricted to one lane at times through the work zone during nighttime hours only.

The restrictions are necessary to perform shoulder work and for placement of temporary pavement in preparation for future shifts in traffic patterns.

Lane restrictions generally occur from 9 p.m. to 7 a.m. each night.

Two lanes in each direction are maintained on I-75 during daytime hours.

The I-75 northbound lanes from the U.S. 68/state Route 15 interchange to county Road 99 have been shifted to the right onto the outside shoulder.

Setting of concrete barrier is ongoing throughout this section in the northbound direction.

Once the barrier is in place, construction operations during daytime hours will increase.

The legal speed through the work zone is reduced when workers are present.

Speed limits are displayed via electronic message boards which display the legal, posted speed through the zone.

I-75 southbound in the U.S. 68/state Route 15 interchange area is shifted to the outside shoulder for a short distance and then back during removal of the existing barrier wall.

Removal of the barrier wall is occurring during daytime hours.

The change in traffic pattern will continue for approximately another week.

North of Findlay

Through July, single lane restrictions are possible on I-75 between U.S. 20 and county Road 99 for finish work.

All six lanes of I-75 between Oil Center Road and county Road 99 are now open, following the lane restrictions necessary for paving operations.

Project complete: October. All work is weather permitting.

U.S. 68/State Route 15 Interchange with I-75

The exit ramp from I-75 northbound to U.S. 68/state Route 15 (exit 156) is expected to close June 19 for approximately three years. At that time, traffic will be detoured north to the state Route 12 interchange to I-75 southbound back to U.S. 68/state Route 15. (See detour map)

Related Construction

Harrison Street over Interstate 75

Harrison Street over Interstate 75 closed May 15 for approximately nine months for reconstruction.

Demolition of the existing Harrison Street bridge has been completed.

Traffic on I-75 in the area of Harrison Street will be restricted to one lane at times for work related to the reconstruction of the bridge.

Access to the Oakwoods Nature Preserve during the closure of the Harrison Street overpass will be available at all times during construction by accessing county Road 144 from the north via Sandusky Street.

Service road construction

Construction of a service road off Lima Avenue connecting to Lake Cascades north of the U.S. 68/state Route 15 interchange is under way. Construction is expected to be complete late this summer.

Noise wall construction

Construction of noise walls in designated areas is expected to begin in late June or early July.

Work is expected to begin in the south end of the project area and proceed to the north.

Construction of all noise walls is expected to be completed in July 2018.

Hardin County

Bridge repairs

State Route 31 between township Road 265 and state Route 273 will close June 26 for 60 days for bridge repair at two locations: one over Panther Creek just south of township Road 206, the second over Wolf Creek north of township Road 265. Traffic detoured onto state Route 292 and state Route 273 back to state Route 31. Work is being performed by Crossroads Construction, Cambridge. (See detour map 1, map 2)

State Route 195 over Cottonwood Ditch, south of McGuffey, between the north and south jog of Cottonwood Road, closed June 5 for 60 days for bridge repair. Traffic detoured onto county Road 110, state Route 235 and state Route 309 back to state Route 195 Work is being performed by Crossroads Construction, Cambridge. (See detour map)

Drainage tile repairs

State Route 81 at township Road 55, east of Ada, will be restricted to one lane through the work zone for drainage tile repair. Work is being performed by the ODOT Hardin County maintenance garage.

Logan County

State Route 274 between State Route 235 and State Route 117, Daily lane closures June 12th – July 31st between the hours of 7 am and 5 pm. One lane will remain open for travel in each direction through the use of flaggers.

US 33 west between State Route 274 and State Route 117, Daily ROAD CLOSURES June 9th – 12th between the hours of 7 am and 5 pm. The official detour is: State Route 117 to State Route 274 to US 33. *US 33 east will remain open.

US 33 between McCalla Road and State Route 117, Daily lane closures June 6th – 30th between the hours of 7 am and 6 pm. One lane will remain open for travel in both directions through the use of flaggers.

State Route 366 between Township Road 94 and State Route 117, Daily lane closures May 8th – July 31st between the hours of 7:30 am and 5 pm. One lane will remain open for travel in both directions through the use of flaggers.

State Route 368 between State Route 366 and the county line, Daily lane closures May 8th – July 31st between the hours of 7:30 am and 5 pm. One lane of traffic will remain open through the use of flaggers.

State Route 117 between State Route 235 and State Route 274, Daily lane closures May 8th – July 31st between the hours of 7:30 am and 5 pm. One lane of traffic will remain open through the use of flaggers.

US 68 between TR 219 and County Road 103, Lane closures April 10th – June 30th. One lane will remain open at all times for travel in each direction through the use of flaggers.

Mercer County

US 33 at US 127, Intermittent lane closures May 22nd – September 15th between the hours of 7 am and 3 pm. One lane will remain open in each direction at all times.

State Route 707 between Indiana State line and US 33, Daily lane closures April 21st – July 24th between the hours of 7 am and 7 pm. One lane will remain open in each direction.

US 127 between State Route 705 and State Route 219, Daily lane closures June 19th – July 31st between the hours of 7 am and 7 pm. One lane will remain open for travel in each direction through the use of flaggers.

Putnam County

Tarring and chipping

State Route 12 from state Route 115 to the Hancock County line will be reduced to one lane through the work zone to remove pavement markings in preparation for pavement repairs. Work is being performed by the ODOT Putnam County maintenance garage.

Contact: Rhonda Pees, public information officer, ODOT District 1

(419) 999-6803; [email protected]

Shelby County

State Route 66 between Enterprise Drive and Greenback Road, ROAD CLOSURE April 24th – June 14th. The official detour is: State Route 47 to I-75 to State Route 29 to State Route 705

Amsterdam Road between County Road 25A (Sidney) and Heiland Kies Road, ROAD CLOSURE May 15th – August 15th. The official detour is: Amsterdam Road to County Road 25A to State Route 274 to Heiland Kies Road to Amsterdam Road

State Route 66 between Enterprise Drive and Greenback Road, ROAD CLOSURE July 10th – October 13th. The official detour is: State Route 47 to I-75 to State Route 29 to State Route 705

Van Wert County

Tarring and chipping

U.S. 224 from U.S. 127 to the Putnam County line will be restricted to one lane through the work zone for the tarring and chipping of the roadway. Work is being performed by the ODOT Van Wert County maintenance garage.

Delayed closure

State Route 637 closure between Feasby Wisener Road and Elm Sugar Grove Church Road has been delayed indefinitely due to flooding and will be rescheduled. (See detour map)

Pavement repair

U.S. 30 from just east of township Road 127 to just east of county Road 185 restricted to one lane through the work zone for pavement and joint repair and drainage improvements. Work is being performed by Shelly Company, Findlay.

.neFileBlock {
margin-bottom: 20px;
}
.neFileBlock p {
margin: 0px 0px 0px 0px;
}
.neFileBlock .neFile {
border-bottom: 1px dotted #aaa;
padding-bottom: 5px;
padding-top: 10px;
}
.neFileBlock .neCaption {
font-size: 85%;
}

http://www.limaohio.com/wp-content/uploads/sites/54/2017/06/web1_ConstructionBarrels-3.jpg

Ohio Department of Transportation Districts 1 and 7