State Route 12, State Route 115, State Route 613 resurfacing: State Route 12, State Route 115, and State Route 613 in Putnam, Allen, and Hancock counties at the following locations will be restricted to one lane through the work zone beginning Aug. 19 for resurfacing.

State Route 12: Throughout Allen County.

AUGLAIZE COUNTY

Interstate 75 Lane Shift – Expect two lanes on I-75 in each direction. Southbound traffic in the left lane will cross over into a contraflow lane on the northbound side just south of the rest areas starting Thursday, June 6 through October 2024. Vehicles in the contraflow lane will not have access to exit 113 for SR 67. Drivers will re-enter the southbound driving lane just north of Middle Pike. Crews will be reconstructing the southbound travel lane bridge. This new traffic pattern will maintain two lanes of traffic in each direction. This shift is weather dependent.

Interstate 75 Lane Closures – Expect intermittent overnight lane closures on I-75 in both directions between Middle Pike and Hengstler Road from 6 p.m. to 7 a.m. starting Monday, March 18 through Friday, November 1. Crews will be performing bridge work.

HARDIN COUNTY

State Route 31 reconstruction: Main Street between Ohio Street and Carrol Street in the city of Kenton closed on March 4 for 240 days for reconstruction, curb and gutter, and sewer. Detour: U.S. 68/Detroit St. to Letson Ave., back to SR 31/Main St.

PUTNAM COUNTY

U.S. 224 railroad repair, Ottawa: U.S. 224 at the railroad tracks between Moe. Street and Agner Street in the village of Ottawa will close on Wednesday, Oct. 2, for approximately seven days for crossing repair work. Detour: SR 65 to SR 12 to CR 5, back to U.S. 224.

State Route 12, State Route 115, State Route 613 resurfacing: State Route 12, State Route 115, and State Route 613 in Putnam, Allen, and Hancock counties at the following locations will be restricted to one lane through the work zone beginning Aug. 19 for resurfacing.

State Route 12: From the village of Vaughnsville to the Allen County line. From the Allen County line to the west corporation of Columbus Grove. From the east corporation of Columbus Grove to the Hancock County line.

State Route 115: Through the village of Kalida.

State Route 613: Through the village of Leipsic.

State Route 15 guardrail upgrade: State Route 15 between Road 13 and Township Road 12-H will be restricted to one lane via temporary traffic signals the week of Sept. 23 for guardrail upgrades.

Sycamore Street, Columbus Grove, intersection improvement: Sycamore St. at State Route 65, on the east side of the intersection, will close Thursday, Sept. 12 for approximately 60 days to add a new right-turn lane and additional roadway improvements. On State Route 65, two lanes in both directions will remain open throughout the project. Detour: SR 12 to SR 65, back to Sycamore St.

VAN WERT COUNTY

U.S. 30 rest area reconstruction: The U.S. 30 rest areas between State Route 49 and U.S. 127 in Van Wert County closed on January 11 for approximately one year for complete reconstruction of the buildings.

U.S. 30 bridge repair: Converse Roselm Road and Stripe Road over U.S. 30 closed in May due to damage caused by an over-height vehicle. Repair is underway and reopening of the overpasses is expected in early November.

Along U.S. 30, the median at Mendon Road and Boroff Road is closed; traffic will be restricted to right-in, right out movements only.

U.S. 30 is restricted to one lane through the work zone.

U.S. 127 resurfacing: U.S. 127 between the Mercer County line the city of Van Wert is restricted to one lane for resurfacing.

State Route 81 pavement repair: State Route 81 between U.S. 127 and the Auglaize County line will be restricted to one lane, alternating one-way, on Monday-Tuesday, Sept. 30-Oct. 1, for pavement repair.

State Route 81 reconstruction: State Route 81 between Willshire Eastern Road and Harrison Willshire Road, just east of the village of Willshire closed on May 6 for approximately 150 days to raise the roadway profile and replace two culverts. Access for local traffic to all properties will be maintained throughout construction. Detour: SR 49 to U.S. 33 to SR 118, back to SR 81.

State Route 697 pavement repair: State Route 697 near Spencerville Delphos Road on the west side of the between the city of Delphos will be restricted to one lane, alternating one-way, on Wednesday-Thursday, Oct. 2-3, for pavement repair.

Leeson Avenue reconstruction: Leeson Avenue between Shannon Street (State Route 118) and Rose Drive in the city of Van Wert closed on Feb. 7 for 245 days for reconstruction including curb and gutter, storm sewer, and a multi-use path on the north side of the roadway.